Hello Saurabh,
Thank you for your inputs. Below is the output of CJI5.
Ref,Doc Category Debit Date Oty Object Cost Elem. Val/CO Area Crcy Total Qty. UM
PREQ 28.05.2014 WBS XXXXXX XXXXXX 0.00 0 EA
POrd 28.05.2014 WBS 14,000.00 1000 EA
From the above output i think system is not capturing the PR commitment. I'm not sure as i'm basically into MM and dont know much about PS.
Why the system is stopping with budget exceeded error at the time of PR creation and not giving any error while changing the PR value after PO creation. System is giving budget exceeded error if quantity is changed in PR. Please explain the standard system behavior and suggest how to enable control at the time of PR value change.
Thanks in advance.